Newton Public Works & Community Services Alerts

◄ Back
August 19, 2022 8:50 AM

Downtown Streetscape Project Update

The City of Newton’s contractors continue working on the next downtown streetscape project. We appreciate your patience.

Facebook Twitter Email

Latest Update:

November 3, 2022 10:42 AM

In-Roads will begin the next part of the downtown streetscape project on Monday, November 7. They will mill the existing asphalt and then immediately complete the HMA paving. They plan to start on W 3rd St S on Monday morning and east to W 2nd St S, E 2nd St S and E 3rd St S. In-Roads expects to complete the project on Wednesday, November 9. Parking will be restricted on all four streets beginning on Monday and the roads will be closed during the milling and paving. If you have questions, please call the City of Newton Public Works Department at 641-792-6622.

Prior Updates

October 11, 2022 8:54 AM

Caliber Concrete will be closing E 2nd St S on October 11, 2022 to begin pavement removals. W 2nd St S continues to be closed while storm sewer work is completed. 

October 4, 2022 9:04 AM

Caliber Concrete has closed the 100 block of W 2nd St S as they continue the downtown streetscape project. They have reopened the 100 block of E 3rd St S to traffic.

September 26, 2022 8:36 AM

Caliber Concrete has closed the 100 block of W 2nd Street S starting September 26 through October 14 as they continue working on the next phase of the Downtown Streetscape Project.

September 20, 2022 9:37 AM

Caliber Concrete will be closing the 100 block of E 3rd Street S from September 13 through September 27.