Current Projects

Northwest Downtown Parking Lot Closure

The Northwest Downtown parking lot will be closed Thursday, Decembre 19 until Saturday, December 21 for final cleanup and punch list work.

Questions on this project can be directed to the Public Works Department at 641-792-6622. Below is a map that shows the parking lot impacted by this project as well as an alternate parking lot (located near the DMACC Campus at W 4th St N and N 2nd Ave W). Click here to view a larger PDF of the map.

Alternate-parking-map

Arbor Estates Plat 1

Construction is scheduled to begin the week of October 14th (weather dependent). At this time, Seamus Excavating, the project contractor, will be mobilizing equipment to begin excavation to grade out the project site. Seamus Excavating anticipates the excavation and grading work to take about 3 weeks.

After this storm sewer, sanitary sewer, and water main will be installed, which is anticipated to take about 6 weeks. Once underground utility work is completed, street paving operations will take place. The final stage of the project will be site restoration and cleanup. 

This project is scheduled to be completed by the end of May 2020.

Arbor Estates Plat 1